Patli and Jamalpur flyovers on Gurugram-Pataudi-Rewari highway targeted for early September opening

Featured image for the article: Patli and Jamalpur flyovers on Gurugram-Pataudi-Rewari highway targeted for early September opening

NHAI expects the two nearly finished flyovers to open in the first week of September as it works towards completing most of the 45-km corridor by month-end.

The Patli flyover beside Adani Logistics Park and the Jamalpur flyover, about 5 km away, are each around 90% complete. NHAI expects the route to draw an estimated 70% of Gurugram-Rewari traffic away from the Delhi-Jaipur Highway once it is fully operational.

Two flyovers on the Gurugram-Pataudi-Rewari highway — at Patli, beside Adani Logistics Park, and at Jamalpur, about 5 km away — are expected to open in the first week of September.

Both structures are around 90% complete and are receiving finishing work, NHAI officials said. Their opening follows the launch of the 7-km Pataudi bypass earlier this month; officials said traffic has picked up on that stretch and congestion inside Pataudi town has reduced.

NHAI is targeting September-end for completion of most of the 45-km highway. The exceptions are the railway overbridge at Pahadi village, where about 30% of work is complete, and a flyover at Dwarka Expressway; both are scheduled for 2027.

The project includes 81 culverts, 23 vehicular underpasses, one railway overbridge and two flyovers. It is estimated to cost about ₹1,900 crore, including ₹600 crore for land acquisition. NHAI estimates that once the new route is operational, roughly 70% of Gurugram-Rewari traffic could move off the Delhi-Jaipur Highway.